Transmission Project Review Process

With the passage of CPUC Resolution E-5252 on April 27, 2023, the Commission established the Transmission Project Review (TPR) Process for the state’s investor-owned electric utilities (IOUs) beginning January 1, 2024. The purpose of the TPR Process is to have a uniform process to review IOUs’ capital transmission projects, allowing the CPUC and Stakeholders to receive robust data from Transmission Owners, and to inquire about and provide feedback on the IOUs’ historical, current, and forecast transmission projects.
The TPR Process provides useful information to numerous programs and proceedings at the CPUC. These include: California Environmental Quality Act (“CEQA”) review and permitting, Integrated Resource Planning (“IRP”), the Distributed Energy Resources (“DER”) Action Plan, General Rate Cases (“GRC”), wildfire mitigation and recovery efforts, and the CPUC’s Risk-Based Decision-Making Framework (“RDF”) and Risk Assessment & Mitigation Phase (“RAMP”).
The descriptions of data fields to be included in the TOs' transmission project data is linked here: Resolution E-5252 Atch B TPR Process Data Template.
Pacific Gas and Electric
Pacific Gas and Electric (PG&E) will release its next transmission project data on May 1, 2025. PG&E directs Stakeholders to its website for all publicly available documents and data releases, listed under the case-name "Transmission Project Review (TPR) Process [Res.E-5252]." This also includes a non-disclosure agreement (NDA) that eligible Stakeholders can submit to access PG&E’s confidential data. Please direct all PG&E-specific comments and questions, including NDA submissions, to tprprocess@pge.com.
Please see the table below for the schedule of PG&E’s upcoming TPR Process cycle, which begins on May 1, 2025.
PG&E TPR Process Schedule: May 2025 – September 2025 (UPDATED 04/18/25)
EVENT |
DATE |
Data released |
May 1 |
Date by which Stakeholders provide questions and comments |
June 16 |
Written responses to Stakeholder questions and comments |
July 7 |
Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting |
July 14 |
Stakeholder Meeting |
July 29 |
Stakeholders’ questions and comments related to Stakeholder Meeting |
August 13 |
Written responses to questions and comments related to Stakeholder Meeting |
September 4 |
Last day for Stakeholders to submit project-specific, follow-up questions |
September 12 |
Written responses to Stakeholder project-specific follow-up questions |
September 26 |
Last day for Stakeholders to submit comments. There is no expectation of written responses. |
September 30 |
Southern California Edison
Southern California Edison (SCE) released its most recent transmission project data on December 2, 2024, and will release its next data spreadsheet on June 2, 2025. SCE directs Stakeholders to its website for all publicly available documents and data releases, listed under the drop-down menu for “2024.” Requests to receive and submit a non-disclosure agreement (NDA) for eligible Stakeholders can be directed to ferccaseadmin@sce.com.
Please see the table below for the schedule of SCE’s current December 2024 TPR Process cycle.
SCE TPR Process Schedule: December 2024 – April 2025 (UPDATED 04/18/25)
EVENT |
DATE |
Data released |
December 2 |
Date by which Stakeholders provide questions and comments |
January 15 |
Written responses to Stakeholder questions and comments |
February 6 |
Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting |
February 13 |
Stakeholder Meeting |
February 28 |
Stakeholders’ questions and comments related to Stakeholder Meeting |
March 14 |
Written responses to questions and comments related to Stakeholder Meeting |
April 4 |
Last day for Stakeholders to submit project-specific, follow-up questions |
April 11 |
Written responses to Stakeholder project-specific follow-up questions |
April 25 |
Last day for Stakeholders to submit comments. There is no expectation of written responses. |
April 30 |
San Diego Gas & Electric
San Diego Gas & Electric (SDG&E) released its most recent transmission project data on January 2, 2025, and will release its next data spreadsheet on July 1, 2025.
SDG&E has created a TPR Process-specific webpage where relevant information can be found. This includes the public version of the data and instructions on how eligible Stakeholders can execute a non-disclosure agreement (NDA) to access SDG&E’s confidential data. Please direct all SDG&E-specific comments and questions, including NDA-related matters, to Kris Bourbois (kbourbois@sdge.com).
Please see the table below for the schedule of SDG&E’s current January 2025 TPR Process cycle.
SDG&E TPR Process Schedule: January 2025-June 2025 (UPDATED 04/18/25)
EVENT |
DATE |
Data released |
January 2 |
Date by which Stakeholders provide questions and comments |
February 14 |
Written responses to Stakeholder questions and comments |
March 10 |
Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting |
March 17 |
Stakeholder Meeting |
April 1 |
Stakeholders’ questions and comments related to Stakeholder Meeting |
April 16 |
Written responses to questions and comments related to Stakeholder Meeting |
May 7 |
Last day for Stakeholders to submit project-specific, follow-up questions |
May 13 |
Written responses to Stakeholder project-specific follow-up questions |
May 27 |
Last day for Stakeholders to submit comments. There is no expectation of written responses. |
June 2 |
Please check this webpage for future updates and reach out to Energy Division with any questions about the TPR Process at TPRProcess@cpuc.ca.gov.