With the passage of CPUC Resolution E-5252 on April 27, 2023, the Commission established the Transmission Project Review (TPR) Process for the state’s investor-owned electric utilities (IOUs) beginning January 1, 2024. The purpose of the TPR Process is to have a uniform process to review IOUs’ capital transmission projects, allowing the CPUC and Stakeholders to receive robust data from Transmission Owners, and to inquire about and provide feedback on the IOUs’ historical, current, and forecast transmission projects.

The TPR Process provides useful information to numerous programs and proceedings at the CPUC. These include: California Environmental Quality Act (“CEQA”) review and permitting, Integrated Resource Planning (“IRP”), the Distributed Energy Resources (“DER”) Action Plan, General Rate Cases (“GRC”), wildfire mitigation and recovery efforts, and the CPUC’s Risk-Based Decision-Making Framework (“RDF”) and Risk Assessment & Mitigation Phase (“RAMP”).

The descriptions of data fields to be included in the TOs' transmission project data is linked here: Resolution E-5252 Atch B TPR Process Data Template.

 

Pacific Gas and Electric

Pacific Gas and Electric (PG&E) will release its next transmission project data on May 1, 2025. PG&E directs Stakeholders to its website for all publicly available documents and data releases, listed under the case-name "Transmission Project Review (TPR) Process [Res.E-5252]." This also includes a non-disclosure agreement (NDA) that eligible Stakeholders can submit to access PG&E’s confidential data. Please direct all PG&E-specific comments and questions, including NDA submissions, to tprprocess@pge.com.

Please see the table below for the schedule of PG&E’s upcoming TPR Process cycle, which begins on May 1, 2025.

PG&E TPR Process Schedule: May 2025 – September 2025 (UPDATED 04/18/25)

EVENT

DATE

Data released

May 1

Date by which Stakeholders provide questions and comments

June 16

Written responses to Stakeholder questions and comments

July 7

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

July 14

Stakeholder Meeting

July 29

Stakeholders’ questions and comments related to Stakeholder Meeting

August 13

Written responses to questions and comments related to Stakeholder Meeting

September 4

Last day for Stakeholders to submit project-specific, follow-up questions

September 12

Written responses to Stakeholder project-specific follow-up questions

September 26

Last day for Stakeholders to submit comments. There is no expectation of written responses.

September 30

 

Southern California Edison

Southern California Edison (SCE) released its most recent transmission project data on December 2, 2024, and will release its next data spreadsheet on June 2, 2025. SCE directs Stakeholders to its website for all publicly available documents and data releases, listed under the drop-down menu for “2024.” Requests to receive and submit a non-disclosure agreement (NDA) for eligible Stakeholders can be directed to ferccaseadmin@sce.com.

Please see the table below for the schedule of SCE’s current December 2024 TPR Process cycle.

SCE TPR Process Schedule: December 2024 – April 2025 (UPDATED 04/18/25)

EVENT

DATE

Data released

December 2

Date by which Stakeholders provide questions and comments

January 15

Written responses to Stakeholder questions and comments

February 6

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

February 13

Stakeholder Meeting

February 28

Stakeholders’ questions and comments related to Stakeholder Meeting

March 14

Written responses to questions and comments related to Stakeholder Meeting

April 4

Last day for Stakeholders to submit project-specific, follow-up questions

April 11

Written responses to Stakeholder project-specific follow-up questions

April 25

Last day for Stakeholders to submit comments. There is no expectation of written responses.

April 30

 

San Diego Gas & Electric

San Diego Gas & Electric (SDG&E) released its most recent transmission project data on January 2, 2025, and will release its next data spreadsheet on July 1, 2025.

SDG&E has created a TPR Process-specific webpage where relevant information can be found. This includes the public version of the data and instructions on how eligible Stakeholders can execute a non-disclosure agreement (NDA) to access SDG&E’s confidential data. Please direct all SDG&E-specific comments and questions, including NDA-related matters, to Kris Bourbois (kbourbois@sdge.com).

Please see the table below for the schedule of SDG&E’s current January 2025 TPR Process cycle.

SDG&E TPR Process Schedule: January 2025-June 2025 (UPDATED 04/18/25)

EVENT

DATE

Data released

January 2

Date by which Stakeholders provide questions and comments

February 14

Written responses to Stakeholder questions and comments

March 10

Date by which Stakeholders and CPUC provide agenda items for upcoming Stakeholder meeting

March 17

Stakeholder Meeting

April 1

Stakeholders’ questions and comments related to Stakeholder Meeting

April 16

Written responses to questions and comments related to Stakeholder Meeting

May 7

Last day for Stakeholders to submit project-specific, follow-up questions

May 13

Written responses to Stakeholder project-specific follow-up questions

May 27

Last day for Stakeholders to submit comments. There is no expectation of written responses.

June 2

 

Please check this webpage for future updates and reach out to Energy Division with any questions about the TPR Process at TPRProcess@cpuc.ca.gov.