SCE 2022 RAMP
2022 SCE Risk Assessment Mitigation Phase (RAMP) Proceeding
Now concluded and closed, SCE’s 2022 RAMP application, identified and quantified nine primary risk categories with proposed mitigation plans to reduce their associated risks and consequences to a reasonable level at a reasonable cost. The rulemaking yielded a Staff Report with a finding of general adequacy of the SCE document and its proposals, as well as Decision D.23-11-007, which noted that final Commission approval of SCE’s proposed mitigations to its safety risks and associated spending are to be addressed within the utility’s application A.23-05-010 for its 2025 General Rate Case: “Any deficiencies and shortcomings that may still exist following integration of RAMP proposals and party comments into the GRC shall factor into whether the RAMP proposals and its associated costs shall be authorized.”
It is expected that SPD’s findings and conclusions will enable the Commission to make an informed decision regarding the utility’s proposed future four-year funding period for years 2025 through 2028 for programs intended to address Edison’s most critical safety risks associated with delivering energy, including the operation and maintenance of its assets.Filed May 13, 2022 in support of SCE’s 2025 GRC application, SCE’s 2022 RAMP application was assigned Commission docket card number A.22-05-013.
Nine Principal Safety Risks Identified within SCE 2022 RAMP
Source: SCE 2022 RAMP, Chapter 1, p. 2
Commission requirements for approval of SCE’s 2025-2028 multibillion-dollar-a-year risk-mitigation spending plan will include a demonstrated safety program of proposed mitigation measures to reduce the utility’s identified top risks, which include Wildfire, Cyber Attack, Natural Disaster, and Sabotage (physical security) to a reasonable level and at a reasonable cost. Generally, all energy utility risk assessment projects within a RAMP application are expected to describe three mitigation plan alternatives with a justified utility-preferred alternative. Additional RAMP requirements include cost and risk-reduction estimates for the three mitigation plan alternatives.
As shown in the figure below, the 2022 SCE RAMP application will inform the utility’s risk and safety spending for the four-year period 2025 through 2028.
SPD Staff Evaluation Report of SCE 2022 RAMP Application, November 10, 2022
Public Engagement Efforts
Public Workshops
RASA-Moderated Workshops
More information provided at a later date
Useful Links
2022 SCE RAMP Application, made available May 13, 2022
Staff Evaluation Report appraising SCE 2022 RAMP Application and risk methodology, November 10, 2022
Assigned Commissioner Scoping Memo and Ruling, issued September 19, 2022.
Pre-Hearing Conference Statement by SCE proposing RAMP scope and schedule, August 10, 2022
SCE 2022 RAMP Data Transparency Submission, dated July 12, 2022, in compliance with Commission Decision D.21-11-009
General Rate Case Primer
SCE 2025 GRC Application